Field Report: EIFS Stucco Termination Issues Fixed in Northville
Phase 1: Analysis (Before)
The bottom of the EIFS stucco terminates below grade and is currently buried in the dirt.
The EIFS stucco on the wall section next to the front entrance requires cutting back 8 to 10 inches for conversion to a drainage system.
The bottom 8 to 10 inches of the EIFS stucco requires removal from the outside corner to the brick to incorporate a new drainage system. An existing V-groove in the synthetic stucco, approximately 24 inches from grade, will serve as the clean termination point for the new work.
Phase 2: Restoration (During)
After removal of the old synthetic stucco, the underlying brick substrate was exposed. The brick exhibited an uneven surface with significant cement residue, rendering it unsuitable for direct EIFS foam application. The project included smoothing the brick and installing cement board to create a proper substrate for the EIFS system.
Cement board was installed to create a flat, solid surface for the new EIFS foam to adhere to.
The pre-basecoated EIFS starter boards were installed. The project shows clear progress. Correcting the EIFS foam's termination point at grade is critical to prevent future moisture problems.
Phase 3: Completed (After)
The finish coat looks great. Another happy customer
Defective termination points were resolved. The soft, flaking, and peeling top coat was fully repaired.
The project's initial assessment focused on the building's lower EIFS stucco, which was found to be too close to the ground, with some sections even buried in the surrounding soil. This area, particularly near the front entrance and extending from an outside corner to the brick, required significant changes. Plans were made to cut back the synthetic stucco by eight to ten inches. The removed material would be replaced with a new system designed to help water drain away effectively. An existing V-groove in the stucco, located about two feet from the ground, was identified as the clear stopping point for this work.
During the execution phase, the guys carefully removed the old synthetic stucco. This process revealed that the underlying brick surface had a significant amount of old cement, which was not suitable for directly attaching new EIFS foam. The team addressed this by smoothing the brick surface and then applying cement board to create a flat, even, and proper base. With these preparations complete and pre-basecoated starter boards in place, the exterior insulation system began to take its intended form. A critical part of the work involved correcting the issue of foam insulation being too close to the ground level, ensuring better long-term performance.
Upon completion, the EIFS finish coat looked really good. The customer was very happy with the work. Additionally, any soft, flaking, or peeling outer layers of the original finish were fully repaired, resulting in a refreshed and structurally sound exterior.